A repeatable review routine that preserves schedule credibility.
1) Update progress on active tasks.
2) Scan critical path and near-critical paths.
3) Review FNLT violations and upcoming milestones.
4) Confirm expected finish dates with owners.
5) Decide on any plan adjustments, explicitly.
The planner stays in control, updates are incorporated without silent rescheduling, and changes are intentional and communicable.